Follow me as I build a 12 foot catboat from plywood and pine. The boat was designed by Edson Schock in the 1940's. This is a project born of a desire to have another boat to sail here in Puerto Rico that will stand-up to the Trade winds. The sail plan will be changed to a gaff rigged sail. All the lumber is locally bought and pine will be substituted for oak, which is not readily available here. Marine plywood will be used.
Sunday, August 30, 2009
Assembling the Centerboard Box
Wednesday, August 26, 2009
Painting the Inside of the CB Box
I am using an Anti-fouling paint that contains Cuprous oxide or copper powder suspended in the paint. It is a heavy can and the copper will discourage marine life from growing onto a surface, copper being toxic to most living things.
The paint requires almost constant stirring to ensure the copper remains suspended in the paint.
It goes on thick and I have taped off the area where the other headledge gets glued so that the surface remains clean.
Attaching the Sides to the Bedlogs
I understand tat you should no countersink plywood but there are times when it cannot be avoided and this is one of those times.
I mixed a batch of glue, slathered it on to the 2x6 and waxed the screws, sinking them by hand with the bit brace.
It turned out right and tomorrow I will do the other side!
Thursday, August 20, 2009
Shaping the Centerboard Box
I had about 1-1/2" to remove in the forward part and 3/4" of wood to removed in the back and what would have taken me at least 4 hours was accomplished in 30 minutes!
Gotta love it!
Wednesday, August 19, 2009
Assembling the Centerboard Box
The plywood panels assembled with the pine end pieces.
Cutting the 2 x 6's
After checking for the initial fit of the pine board to the plywood, I added the 2 x 6's to the form to complete the mock up for fitting into the slot I had cut into the keel.
I had already removed frames 5, 6 & 7 in order to be able to lift and place the keel box. I had chiseled and rasped the openings to widen and square them a little more to get the right fit.
Placing my hydraulic lift under the center of the box, I lifted it into position, plumb with the face of frame #4.
This is not the final position but serves to illustrate the concept about how I will now transfer a parallel curved line of the keel to the sides of the 2 x 6's to allow a nice watertight fit against the keel. I will shave that down with the power planer.
More on that in the next installment!
Thursday, August 6, 2009
Cutting the Centerboard Slot
I have made a 3/4" wide opening along the center line of the keel. This will be the first step in the construction of a "box" to contain it when it is in an upright position.
It was a fairly easy operation. Drawing the limits out in pencil, I plunged my circular saw into the wood and cut it from one end to the other.
I finished the cut with my hand saw then used my saber saw to cut the ends.
Thursday, June 25, 2009
Shaping the keel
I began to work on the keel today. I laid out the batten along the keel slot and marked the position of each frame. I then transferred the frame locations to the keel board. I marked the width of the keel at each frame and laid a batten along these marks to make a curve for the keel shape.
I then took my saber saw and slowly cut the excess wood off from either end. A quick pass of the power planer squared and smoothed everything and it turned out great
Now I will wet it and, putting 2 blocks (cat is optional) in the middle, put some curvature into it to make it easier to set it into the boat.
Wednesday, June 24, 2009
Cutting the Keel
Wednesday, June 3, 2009
Building the Foundation and Setting the Frames
The foundation
After marking the center of the foundation at both ends, I cut two 1-foot 2x4’s and shimmed them to be level with the foundation and attached them with deck screws. Taking the bow stem and placing the 48” ruler to mark the forward most point for the stem, I took the angle of the stem from the full size drawing and set it correctly, making sure it was square and dead center to the foundation. A hefty 6” clamp will hold it in place.
That went pretty quick too so on to marking out the positions for the 10 frames and the transom. These were double-checked for accuracy by comparing measurements from the front and back of the foundation.
With this done I wanted to see if I could get a couple frames mounted. First, I had to run a mason line to use as a centerline. Measured it out and attached it then I put up frame number 1. I used a plumb bob to align it with the centerline then sank a couple deck screws into the spreader to hold it in place. 2 drills, one for pilot holes and the other as a driver, made quick work out of mounting the frames to the foundation.
3 frames done
5 done!
It went so quickly that I got all 10 and the transom set!